Progress payment due date: 14-day and 30-day rules
RetainerWorth Editorial Team · Published · Checked · 10 min read
For progress payments under the 14-day rule, payment is due 14 days after the designated billing office receives a proper payment request.
Key takeaways
- Check the payment clause before choosing a due-date rule.
- Send a proper request to the designated billing office.
- Record the request date, delivery date, disagreements, and extensions.
- Check your file before following up on a late payment.
Why the due date matters more than the amount
If your firm bills a government agency or a prime contractor on progress payments, cash flow depends on one question: when does the money have to arrive? The invoice goes out, someone says the review is underway, and weeks pass. A managing partner who cannot name the due date cannot plan payroll, pay subcontractors, or judge how much to draw on a credit line.
The federal rules are more specific than most people expect. This post walks through the starting events, conditions, and records that matter for progress payments. It also covers the 30-day progress payment rule, the deemed-approval rule that applies when the agency stays silent, and the fallback for a billing office that never records the date it received your request.
A progress payment is supposed to keep money moving while the work is still underway. If it arrives late, you are financing the work yourself, and each week of delay adds to that cost.
This is general information, not legal advice. Read the payment clauses in your contract before you rely on any number here.
Start with what "proper" means
The FAR's prompt payment clause for fixed-price architect-engineer contracts shows how seriously the rules treat this. It says a proper invoice must include a list of items, set out in its own paragraphs. Acquisition.gov, 52.232-26 That list belongs to that clause, so your contract may require something different. The principle still carries over: the content of the request is part of the payment rule.
Pull the payment clause from your contract, list every item it requires, and build a checklist from that list.
Use the federal legal invoice checks and invoice review checks to organize your review alongside the contract's requirements.
The 14-day rule for approved progress payments
The rule covers progress payments based on contracting officer approval of the estimated amount and value of work or services performed, including payments for reaching milestones in any project. Acquisition.gov, FAR 32.904
Three parts of that sentence matter most.
First, the clock starts when the designated billing office receives the request, not when the project manager gets a copy. Find out which office your contract designates and send the request there, by the method the contract allows. A copy to the project manager may help coordination, but it does not start the clock.
Second, the clock starts only on a proper request. If the request is incomplete, you may be waiting on a clock that has not started. That is why the content check belongs before the request leaves your office.
Third, the rule covers milestone payments. If your billing is tied to milestones, the same clock applies to payments tied to them, as long as the payment rests on contracting officer approval of the estimated work. Check the contract's approval requirements for milestone payments.
Confirm how days are counted before you build a cash plan around the due date.
When the 30-day rule applies instead
The same section sets a different due date for some progress payments. It says the due date for progress payments is the 30th day after Government approval of contractor estimates of work or services accomplished. Acquisition.gov, FAR 32.904
This is where managers get confused. Both rules are about progress payments, and both appear in the same section. Keep the starting events separate when reviewing your payment clause. Those phrases are close enough that a busy reader can mix them up, and the mix-up is expensive.
Read your contract to find out which rule applies to your billing. If your payments fall under the 30-day rule, your cash plan should use 30 days. Using the 14-day number for a 30-day payment leaves you short of cash for the difference.
Deemed approval: the 7-day clock on estimates
Agencies do not always approve estimates in writing on time, and the FAR covers that case. Government approval is deemed to occur constructively on the 7th day after the designated billing office receives the contractor estimates. Acquisition.gov, FAR 32.904
A silent agency therefore does not hold your estimate open indefinitely. Because the 30-day rule counts from approval, the deemed approval date becomes the starting point for that count. The 7-day mark is not the due date, but it moves the due date forward.
The conditions are a proper payment request and no disagreement over quantity, quality, contractor compliance with contract requirements, or the requested progress payment amount. Acquisition.gov, FAR 32.904 If the agency disputes any one of those, do not assume the deemed approval applies. Treat the dispute as a separate problem to resolve in writing.
The rule also lets the agency extend the period, with a condition. The contracting officer must document in the contract file the justification for extending the constructive acceptance or approval period beyond 7 days. Acquisition.gov, FAR 32.904 If you are past day 7 and nobody has explained why, ask the contracting officer in writing whether an extension was made and what the reason was. You are asking for the basis for the delay, not making a demand.
Work through the arithmetic on your own calendar. Count 7 days from the date the billing office received your estimate to find the deemed approval date, then count 30 days from that date if the 30-day rule applies. Then check whether the conditions above were met. If a dispute came in before day 7, the deemed approval may never have started, and a calendar built on it would be wrong.
When the billing office does not record the date
That applies provided the billing office receives a proper payment request and there is no disagreement over quantity, quality, or contractor compliance with contract requirements. Acquisition.gov, FAR 32.904
Two points follow. First, the fallback counts from the date on your request, not from the date the office got it. That date should be accurate and easy to prove. Second, the fallback's list of disagreements is shorter than the one in the deemed approval rule. It names quantity, quality, and contractor compliance, and it does not name the requested payment amount. Do not treat that difference as a loophole. Resolve any disagreement over the amount in writing rather than assuming the fallback settles it.
The practical lesson is to avoid the situation altogether. Keep a dated record of how and when you sent each request.
How the rules fit together
The table summarizes the starting events discussed above. It is a reading aid, not a substitute for the contract or the FAR text.
| Situation | Clock starts | Due date |
|---|---|---|
| Progress payment based on contracting officer approval, including milestones | Billing office receives a proper payment request | 14 days |
| Progress payment based on Government approval of contractor estimates | Government approval | 30 days |
| Constructive approval, subject to the conditions above | 7th day after billing office receives the estimates | Counted from that deemed approval date, under the 30-day rule |
The table shows the clock, not the protection. The protection comes from the conditions, and those are what you need to document.
Request checks before you send
The first is sending the request to the wrong place. Confirm the office, the address, and the method the contract names, and use all three every time.
The second is bundling several payment periods into one request without clear estimates for each.
The third is sending a request before the estimate is final. Numbers that still need internal review invite the disagreements that remove the protection of the deemed approval rules. Reconcile quantities and quality with the project manager first, then send the agreed numbers.
The fourth is treating silence as a dispute, or a dispute as silence. An agency that says nothing may be within its window, or it may have raised an objection in a meeting that never reached your file. Ask for written confirmation of any objection and record the date you received it.
The fifth is mixing up the 14-day and 30-day rules. Write the rule that applies on the cover sheet of each request, so anyone reviewing it knows which clock you are using.
Log the date at the moment of delivery.
Talking to the contracting officer when a payment is late
When a payment passes its due date, check your own file before you call anyone. If your file is in order, you have a clear basis for the conversation. If it is not, fix the gap first, because a weak file makes a strong complaint impossible.
Next, send a short written message to the contracting officer. State the request, the date the billing office received it, the rule you believe applies, and the due date that results. Ask for the status of the approval, and ask whether any extension was made and documented. A question like that is hard to answer with a vague reply.
Do not argue the legal meaning of the FAR in your first message. Ask for the facts, then compare them with the rule. A calm, specific message often clears those up faster than an angry one.
If the matter does not resolve, use the escalation path your contract and the agency's procedures provide. Find that path before you need it. A documented escalation is easier to act on than a general complaint.
What this post does not cover
This post covers the federal rules in the FAR section on payment due dates, plus the related prompt payment clause mentioned above. It also does not cover interest on late payments, formal dispute procedures, or appeals of a contracting officer's decision. Get advice from counsel on those questions before you act.
Nothing here replaces the contract. When the contract and this post differ, the contract controls.
Build a due-date routine
Turn the rules into a routine. Each payment request should get a line in a tracking sheet with these fields: the date the billing office received the request and the date on your copy; the rule that applies; the due date, calculated from the correct starting point; the deemed approval date, if approval is still pending; any disagreement the agency raised, with its date and stated reason; and any extension the agency has told you about, and whether it was documented.
Review the sheet weekly, and more often near payroll dates. A due date that passes without payment should trigger a call that same day. The sheet also helps with planning. If a payment falls under the 14-day rule, you can see early whether to draw on a credit line or hold a hire. If it falls under the 30-day rule, you can plan for a longer gap.
Illustrative example: planning from approval
Suppose your payment falls under the 30-day rule and Government approval has occurred. Record that approval date, count 30 days from it, and enter the resulting due date in your tracking sheet. Keep the approval record with the request so your follow-up uses the same starting event.
Start with the contract
Today, pull the payment clause for your next request and check its required contents against your draft before sending it.
Questions about progress payment due dates
What should I check before following up?
Check the request, delivery record, applicable rule, calculated due date, and any disagreement or documented extension. Keep those records together for the conversation.
Does the deemed approval date mean payment is due that day?
No, deemed approval provides the starting event for the applicable payment period. Check the conditions and any documented extension before using that date in your cash plan.